RoR pondage: capacity and pondage volume

Short answer

Generator capacity is 6.79 MW. Pondage volume needed is about 193,846 m³, calculated from the peak flow deficit over 4 hours.

A run-of-river hydroelectric power station is proposed across a river at a site where a net head of 30 m is available on the turbine. The river carries a sustained minimum flow of 25 m³/s in dry weather and behind the power station sufficient pondage is provided to supply the daily peak load demand with a load factor of 65%. Assuming the plant efficiency of 60%, determine the maximum generating capacity of the generator to be installed at the power house. If the daily load pattern indicates 20 hours average load and 4 hours of peak load, determine the volume of pondage to be provided to supply the daily demand.

Maximum generating capacity

The minimum flow gives the average power available throughout the day:

Pavg=γQHη=9.81×25×30×0.60=4,414.5 kWP_{avg} = \gamma Q H \eta = 9.81\times25\times30\times0.60 = 4,414.5\ \text{kW}

With pondage the plant can follow the daily load, and the load factor is

Load factor=PavgPmax=0.65⇒Pmax=4,414.50.65=6,791.5 kW≈6.79 MW\text{Load factor} = \frac{P_{avg}}{P_{max}} = 0.65 \Rightarrow P_{max} = \frac{4,414.5}{0.65} = 6,791.5\ \text{kW} \approx 6.79\ \text{MW}

Volume of pondage (20 h average load + 4 h peak load)

Peak load: Pmax=6,791.5P_{max}=6,791.5 kW for 4 h. The average over the day must equal PavgP_{avg}, so the off-peak load for 20 h is

Poff=24×4,414.5−4×6,791.520=3,939.1 kWP_{off} = \frac{24\times4,414.5 - 4\times6,791.5}{20} = 3,939.1\ \text{kW}

Flows needed at peak and off-peak (with 9.81×30×0.6=176.589.81\times30\times0.6 = 176.58 kW per m³/s):

Qpeak=6,791.5176.58=38.46 m3/s,Qoff=3,939.1176.58=22.31 m3/sQ_{peak} = \frac{6,791.5}{176.58} = 38.46\ \text{m}^3/\text{s},\qquad Q_{off} = \frac{3,939.1}{176.58} = 22.31\ \text{m}^3/\text{s}

The river supplies 25 m³/s, so the deficit of (38.46−25)(38.46-25) m³/s for 4 hours must come from the pond:

V=(38.46−25)×4×3600=193,846 m3≈1.94×105 m3V = (38.46-25)\times4\times3600 = 193,846\ \text{m}^3 \approx 1.94\times10^5\ \text{m}^3

(During the 20 off-peak hours the pond fills by (25−22.31)×20×3600=193,846(25-22.31)\times20\times3600 = 193,846 m³, the same volume.)

Answer: generator capacity = 6.79 MW; pondage volume ≈ 193,846 m³ (≈ 1.94 × 10⁵ m³).