Skip to main content

Flow duration curve; firm and secondary energy

Short answer

With head 60 m, design discharge 45 m³/s, and 82% efficiency, firm energy is 67.6 GWh, secondary energy is 80.3 GWh, and total annual energy is about 148.0 GWh.

The stream flow record for a hydropower development site is given below. Draw a flow duration curve and determine firm and secondary energy if the available head is 60 m, design discharge capacity is 45 m³/s and overall efficiency is 82%.

MonthJanFebMarAprMayJunJulAugSepOctNovDec
Q (m³/s)303828221632567254463836

Flow duration curve

Rank the monthly flows in descending order and take p=mN+1×100p=\dfrac{m}{N+1}\times100 with N=12N=12.

RankQ (m³/s)Exceedance (%)Q used = min(Q, 45)
1727.745
25615.445
35423.145
44630.845
53838.538
63846.238
73653.836
83261.532
93069.230
102876.928
112284.622
121692.316
 Q (m³/s)
  72 |*
  56 | *
  45 |-+--*-*-----  design flow
  38 |        * *
  30 |           * *
  22 |               *
  16 |                  *
     +----------------------
      0  20  40  60  80 100 %

The FDC is flat at 45 m³/s for about 31% of the time (months with flow above the design flow).

Energy

Constants: H=60H=60 m, η=0.82\eta=0.82, Qd=45Q_d=45 m³/s, 730 h per month.

  • Installed capacity P=9.81×0.82×60×45=21,719P=9.81\times0.82\times60\times45 = 21,719 kW =21.72=21.72 MW
  • Firm energy is based on the flow available all the time (minimum flow 16 m³/s):
Pfirm=9.81×0.82×60×16=7,722 kW,Efirm=7,722×8760=67.65 GWhP_{firm} = 9.81\times0.82\times60\times16 = 7,722\ \text{kW},\quad E_{firm} = 7,722\times8760 = 67.65\ \text{GWh}
  • Total energy with Qused=min⁡(Q,45)Q_{used}=\min(Q,45): sum of used flows = 420 m³/s-months, so mean used flow = 35 m³/s
Etotal=9.81×0.82×60×35×8760=147.98 GWhE_{total} = 9.81\times0.82\times60\times35\times8760 = 147.98\ \text{GWh}
  • Secondary energy =Etotal−Efirm=147.98−67.65=80.33=E_{total}-E_{firm} = 147.98-67.65 = 80.33 GWh

Answer: firm energy ≈ 67.6 GWh; secondary energy ≈ 80.3 GWh; total ≈ 148.0 GWh per year.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Hydropower Engineering chapter 3 questions →