EVA numerical: Koteshwor-Kalanki road subgrade

Short answer

BAC = Rs 13.05 M; after 6 months, PV=4.35 M, EV=3.45 M, AC=4.6 M; CV = -1.15 M, SV = -0.90 M, CPI=0.75, SPI=0.79, EAC=17.4 M. Over budget and behind schedule; if trend continues, final cost Rs 17.4 M.

Sinoma company of China has planned to prepare a Subgrade for Koteshwor to Kalanki road section of 8.7 km length of ring road to be accomplished within 1.5 years at a cost of 1.5 million per kilometer. The data were taken after 6 months of commencement of the work, the work found to be of 2.3 km completed by expending 4.6 million rupees. Perform EVA and draw your conclusion regarding the Chinese performance in Nepalese domain by calculating each component of EVA.

Given: length = 8.7 km, duration = 1.5 years = 18 months, rate = Rs 1.5 million/km. Review after 6 months: work done = 2.3 km, actual cost = Rs 4.6 million.

Budget at completion

BAC=8.7×1.5=13.05 millionBAC = 8.7 \times 1.5 = 13.05\ \text{million}

Planned value (uniform progress): 6 of 18 months planned

PV=618×13.05=4.35 millionPV = \frac{6}{18} \times 13.05 = 4.35\ \text{million}

(planned length = 8.7/3 = 2.9 km)

Earned value

EV=2.3×1.5=3.45 millionEV = 2.3 \times 1.5 = 3.45\ \text{million}

Actual cost AC=4.6AC = 4.6 million

Variances and indices

CV=EV−AC=3.45−4.6=−1.15 millionSV=EV−PV=3.45−4.35=−0.90 millionCPI=3.45/4.6=0.75SPI=3.45/4.35=0.793EAC=BAC/CPI=13.05/0.75=17.4 millionETC=EAC−AC=12.8 millionVAC=13.05−17.4=−4.35 million\begin{aligned} CV &= EV - AC = 3.45 - 4.6 = -1.15\ \text{million} \\ SV &= EV - PV = 3.45 - 4.35 = -0.90\ \text{million} \\ CPI &= 3.45/4.6 = 0.75 \\ SPI &= 3.45/4.35 = 0.793 \\ EAC &= BAC/CPI = 13.05/0.75 = 17.4\ \text{million} \\ ETC &= EAC - AC = 12.8\ \text{million} \\ VAC &= 13.05 - 17.4 = -4.35\ \text{million} \end{aligned}

Percent complete = 3.45/13.05 = 26.4% against 33.3% planned.

Answer: PV = Rs 4.35 M, EV = Rs 3.45 M, AC = Rs 4.6 M, CV = −Rs 1.15 M, SV = −Rs 0.90 M, CPI = 0.75, SPI = 0.79, EAC = Rs 17.4 M.

Conclusion: The contractor is both over budget (it spends Rs 1.33 for every Rs 1 of work earned) and behind schedule (only 2.3 km against 2.9 km planned). If the trend continues, the final cost will be Rs 17.4 M, Rs 4.35 M above the budget, and the project will take longer than 18 months (about 18/0.793 = 22.7 months). The performance is poor; the client should demand a recovery plan, more resources and better management.