- 2081 Baisakh · 8 marks
Highway earthwork for one km length
Short answer
Multiply side-hill section areas by length: cutting 4428.2 m³, filling 244.5 m³ per km. Pavement layers: wearing coat 350 m³, base 1750 m³, sub-base 3500 m³ (width × thickness × 1000 m).
Estimate for the construction of highway for one km length. Cut slope be 1.5:1 and fill slope be 2:1, mid depth of cutting be 0.35 m for two lane road and ground slope be 9:1. The pavement thickness be wearing coat, base course and sub-base over the subgrade 50 mm, 250 mm and 350 mm respectively.
Given data and assumptions
- Two-lane road: carriageway m with m shoulders on both sides (Nepal Road Standard 2070), so formation width m. The earthwork is taken to subgrade (formation) level.
- Cut slope , fill slope , ground cross slope , centre depth of cutting m at every section, so the section is uniform along the 1 km.
- Wearing coat and base course 7.0 m wide; sub-base spread over the full formation width of 10 m.
Earthwork (side-hill section)
At the up-hill edge the ground is m above formation (cutting), and at the down-hill edge it is m (so that side falls below formation and needs filling). The ground cuts the formation level at m from the centre line.
- Up-hill toe: m from the centre line, ground m above formation
- Down-hill toe (filling slope): m, ground m below formation
- Area of cutting m²; area of filling m² (from the co-ordinates of the section).
Pavement quantities for 1 km
| Layer | Working | Volume (m³) |
|---|---|---|
| Wearing coat 50 mm | 350.0 | |
| Base course 250 mm | 1,750.0 | |
| Sub-base 350 mm | 3,500.0 |
Answer: cutting = 4,428.2 m³, filling = 244.5 m³ per km; wearing coat 350 m³, base 1,750 m³, sub-base 3,500 m³. The cost follows by multiplying each quantity by its rate (District Rate) and adding overhead, profit and VAT.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, km 8.50 to km 9.00 · Estimating and Costing, chapter 6
- Road earthwork, four lane NRS-1070 · Estimating and Costing, chapter 6
- Road earthwork, 80 m length (v) · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- RCC slab culvert: brick, wearing coat, GI pipe, steel · Estimating and Costing, chapter 6
- Hill road earthwork, 0-90 m (8 m formation) · Estimating and Costing, chapter 6
- Plain CC pavement thickness by IRC, 7 m highway · Transportation Engineering II, chapter 2
- Equipment for highway and pavement construction · Construction Management, chapter 4 · asked 3×
- Cut and fill volume, 20 m formation width · Surveying I, chapter 9
- Converting two-way slope to one-way slope · Transportation Engineering I, chapter 3 · asked 2×