Chapter 4 · 8 hours
Substation Equipments
IOE past exam questions
Past questions and answers
27 questions set from this chapter, 6 of them more than once. Most asked first.
- Asked 5 times
- 2073 Shrawan · 5 marks
- 2082 Baisakh · 5 marks
- 2081 Baisakh · 4 marks
- 2080 Bhadra · 6 marks
- 2073 Chaitra · 4 marks
Describe the fire fighting system used in power station with necessary diagram.
Answer
The fire fighting system of a power station detects a fire early, raises an alarm and puts it out quickly, so that costly equipment (transformers, generators, cable galleries, oil stores) is saved and people are safe.
Main fire risks
- Transformer and switchgear insulating oil
- Generator windings (insulation, hydrogen in large units)
- Cable trenches and galleries
- Fuel oil and coal stores, battery rooms
Components of the system
+--------+ +-------------+ +-----------------+
| Fire |-->| Fire alarm |-->| Alarm (bells, |
|detector| | control pnl | | lamps) + trip |
+--------+ +------+------+ +-----------------+
| opens deluge valve
+-------+ +------+ v +-------+ +-----------+
| Water |->|Pumps |--->|Deluge |-->| Spray |
| tank | |(el+DG)| | valve | | nozzles |
+-------+ +------+ +-------+ | (on xfmr) |
+-----------+
- Detection: smoke, heat (rate-of-rise) and flame detectors; for transformers, quartz bulb or linear heat detectors placed around the tank.
- Alarm panel: receives detector signals, sounds alarm, shows the zone, trips the equipment and starts the extinguishing system.
- Extinguishing systems:
- Hydrant system: ring main of pipes with hydrant points and hoses, kept pressurised by jockey pump; main electric pump and diesel standby pump.
- Water spray (deluge) / mulsifire system: for transformers; high-velocity water spray forms an emulsion on the oil surface, cools it and cuts oxygen.
- CO flooding system: for generators, control rooms and cable vaults; CO cylinders discharge automatically and dilute oxygen. Used where water would damage equipment.
- Foam system: for oil tanks and fuel stores.
- Portable extinguishers: CO, dry chemical powder and foam types near equipment.
- Passive measures: oil soak pits filled with gravel under transformers, fire walls between transformers, fire-resistant cable coating and fire barriers.
Requirements
- Automatic operation with manual back-up.
- Reliable, separate water supply and standby diesel pump.
- Regular testing of detectors, pumps and cylinders.
- Asked 4 times
- 2070 Asar · 8 marks
- 2081 Bhadra · 6 marks
- 2080 Baisakh · 4 marks
- 2074 Chaitra · 4 marks
Describe how a SCADA system can be implemented in a power system.
Answer
SCADA (Supervisory Control And Data Acquisition) is a computer-based system that collects real-time data from power stations and substations, shows it to operators at a control centre, and lets them control equipment remotely.
Architecture
+-------------------------------+
| Master station (control ctr) |
| SCADA/EMS servers, HMI, data |
| historian, alarm printer |
+---------------+---------------+
| communication
(fibre, PLCC, microwave, radio, GSM)
+------------+------------+
| | |
+---+---+ +---+---+ +---+---+
| RTU 1 | | RTU 2 | | RTU 3 |
+---+---+ +---+---+ +---+---+
| | |
CT, PT, relays, CB aux contacts, OLTC,
transducers in plant / substations
Components
- Field devices: CTs, PTs, transducers, breaker status contacts, tap-position indicators, intelligent electronic devices (IEDs, numerical relays).
- Remote Terminal Unit (RTU): installed at each substation/plant; acquires analog values (V, I, MW, MVAr, f) and digital status (CB open/closed, alarms), converts them to digital data and executes control commands from the master.
- Communication system: carries data between RTUs and master using protocols such as IEC 60870-5-101/104, DNP3, Modbus, IEC 61850. Media: optical fibre (OPGW), PLCC, microwave, radio.
- Master station: servers and software that poll RTUs, process data, raise alarms, store history and run applications.
- HMI: operator consoles with single-line diagrams, trends and alarm lists.
Implementation steps
- Survey the plants/substations and list the points (analog, digital, control) to be monitored.
- Install transducers/IEDs and RTUs in each station and wire them to CTs, PTs, CBs and isolators.
- Build the communication network (e.g. OPGW fibre with PLCC as back-up) and choose the protocol.
- Set up the master station with redundant servers, database of all points and HMI displays.
- Test point-to-point, then commission and train operators.
Functions in a power system
- Data acquisition: voltage, current, power, frequency, energy.
- Supervisory control: open/close CBs, change transformer taps, start/stop units.
- Alarm and event recording with time stamps (sequence of events).
- Trend and historical data for analysis.
- EMS applications: automatic generation control (load–frequency), economic dispatch, state estimation, load shedding.
- Distribution automation: fault location, isolation and restoration.
Advantages
- Fast, accurate information and quick fault response.
- Fewer staff at unmanned substations.
- Better reliability, economy and security of supply.
In Nepal, the NEA Load Dispatch Centre at Siuchatar uses SCADA to monitor and control the integrated grid.
- Asked 3 times
- 2076 Chaitra · 2 marks
- 2078 Bhadra · 2 marks
- 2073 Chaitra · 2 marks
What is main function of reactor in power system network?
Answer
A reactor is a coil of large inductive reactance and very small resistance. Its main function in a power network is to limit the short-circuit (fault) current to a value that circuit breakers and equipment can safely handle.
- It raises the reactance between the source and the fault, so falls and the fault MVA falls.
- It localises the fault so that the voltage on healthy parts of the system does not collapse.
- Shunt reactors also absorb reactive power on long lightly loaded lines to control over-voltage (Ferranti effect).
- Asked 2 times
- 2081 Bhadra · 8 marks
- 2075 Chaitra · 5+5 marks
Two generators each of capacities 40 MVA, 11 kV having their sub transient reactance of 5% and 4% respectively operating in parallel and supplying to a common load by single feeder of reactance 2 Ω. Calculate the fault level when 3-phase to ground fault occurs on the outgoing feeder. Also calculate the value of reactor to be connected in series with 2 Ω reactor to reduce the fault level by 40 %.
Answer
Work in per unit on a common base. Fault level and a reactor of ohms has .
Base: 40 MVA, 11 kV.
G1 40MVA,5% G2 40MVA,4%
| |
====+=====+=======+==== 11 kV bus
|
X=2 ohm feeder
|
F (3-ph fault)
Fault level
Fault current: , so .
Reactor to reduce fault level by 40 %
New fault level MVA.
Answer: Fault level = 58.53 MVA (about 3.07 kA). A reactor of about 1.378 Ω (0.4556 pu on 40 MVA) in series with the 2 Ω feeder reduces it by 40 % to 35.12 MVA.
- Asked 2 times
- 2072 Chaitra · 6 marks
- 2079 Baisakh · 4 marks
Explain the function of various parts of a power transformer with a neat sketch.
Answer
A power transformer transfers power between two voltage levels by mutual induction. Besides the core and windings it has many accessories for cooling, protection and voltage control.
HV bushing LV bushing conservator
| | | | +---------+--breather
| | | | | oil | (silica gel)
vent _|__|________|__|_____+----+----+
===> | oil-filled tank | Buchholz relay
| +--------------------+ |
| | core + HV/LV wndgs | |=== radiators
| +--------------------+ |
| tap changer OTI WTI |
+---------------------------+
drain valve earthing
Parts and functions
| Part | Function |
|---|---|
| Core (CRGO laminations) | Low-reluctance path for flux; laminated to cut eddy loss |
| HV and LV windings (copper) | Carry current; induce voltage in ratio of turns |
| Tank | Holds core, windings and oil; mechanical protection |
| Transformer oil | Insulation and cooling medium |
| Conservator | Takes up oil expansion and contraction; keeps main tank full |
| Breather (silica gel) | Dries the air entering the conservator |
| Buchholz relay | Gas-operated relay between tank and conservator; alarms/trips for internal faults |
| Explosion vent / pressure relief valve | Releases sudden high pressure during severe internal faults |
| Radiators, fans, pumps | Remove heat (ONAN, ONAF, OFAF cooling) |
| Bushings | Bring winding leads out through the tank with insulation |
| Tap changer (on-load/off-load) | Changes turns ratio to control voltage |
| Oil and winding temperature indicators (OTI, WTI) | Show temperature; give alarm and trip, start fans |
| Oil level indicator | Shows oil level in conservator |
| Drain and filter valves | Draining, sampling and filtering oil |
- Asked 2 times
- 2071 Chaitra · 3 marks
- 2073 Chaitra · 4 marks
Describe how communication between two electric sub-stations can be made with Power Line Carrier Communication system.
Answer
Power Line Carrier Communication (PLCC) uses the high-voltage transmission line itself as the medium to send speech, data, telemetry and protection signals between two substations, by superimposing a high-frequency carrier (about 30–500 kHz) on the 50 Hz power.
Substation A Substation B
bus bus
| |
[WT]=========== HV line ================[WT]
| |
[CC] [CC]
| |
[LMU] [LMU]
| |
PLC terminal PLC terminal
(tx/rx: speech, data, teleprotection)
Components and working
- PLC terminal (transmitter/receiver): modulates the speech/data/protection signal on to an HF carrier at the sending end and demodulates it at the receiving end.
- Coupling capacitor (CC): high-voltage capacitor that passes the HF carrier to the line but blocks the 50 Hz power frequency.
- Line matching unit (LMU): matches the impedance of the coaxial cable to the line and, with the CC, forms a high-pass filter; it also provides surge protection and earthing switch.
- Wave trap (line trap): a parallel LC circuit in series with the line, tuned to the carrier frequency. It offers high impedance to the carrier, so the signal does not leak into the substation bus, but negligible impedance to 50 Hz power.
The carrier travels along the line conductors (phase-to-earth or phase-to-phase coupling) to the other substation, where it is picked up through its own CC and LMU.
Uses
- Telephone (speech) between substations and load dispatch centre.
- Teleprotection: carrier-aided distance and inter-tripping.
- SCADA data and telemetering.
Merits
- No separate communication line needed; the line is strong and reliable.
- Economical over long distances.
- 2082 Baisakh · 8 marks
Two generators each of capacities 50 MVA, 11 kV having their sub transient reactance of 5% and 3% respectively operating in parallel and supplying to a common load through a feeder. If a 3 phase to ground fault occurs on the outgoing feeder, calculate the fault current supplied by each generator and fault power on the outgoing feeder. Also calculate the value of reactor to be connected in series with the outgoing feeder to reduce the fault level by 40 %.
Answer
The feeder reactance is not given, so it is taken as negligible: the fault is close to the bus. Fault MVA .
Base: 50 MVA, 11 kV; ; .
G1 50MVA,5% G2 50MVA,3%
| |
====+=====+=======+==== 11 kV bus
| outgoing feeder
F
Fault current and fault power
Current from each generator
Current divides inversely as the reactances:
Reactor for 40 % reduction
New fault MVA MVA.
Answer: kA (G1: 52.49 kA, G2: 87.48 kA), fault power = 2666.7 MVA; series reactor = 0.0125 pu ≈ 0.0303 Ω (fault level becomes 1600 MVA).
- 2081 Baisakh · 4 marks
Explain the function following parts of a power transformer. i) Conservator tank ii) Explosion vent iii) Breather
Answer
i) Conservator tank
A small cylindrical tank mounted above the main tank and connected to it by a pipe (with the Buchholz relay in between).
- Oil expands and contracts with load and temperature; the conservator takes up this change, so the main tank always stays completely full of oil.
- Only the small oil surface in the conservator touches air, which reduces oxidation and moisture absorption.
- Its oil level indicator shows the oil level.
ii) Explosion vent
A bent pipe on top of the main tank, closed by a thin diaphragm (bakelite/glass), or a modern spring-loaded pressure relief valve.
- During a severe internal fault, arcing decomposes oil into gas and pressure rises suddenly.
- The diaphragm bursts and releases the pressure, preventing the tank from bursting or exploding.
iii) Breather
A small container filled with silica gel, with an oil seal cup, fitted on the conservator air pipe.
- When the oil contracts, air is drawn into the conservator through the breather.
- Silica gel absorbs moisture (blue colour turns pink when saturated); the oil cup traps dust.
- This keeps the oil dry and maintains its dielectric strength.
- 2081 Baisakh · 6 marks
The given figure shows three generators operating in parallel. Find the fault current and fault level if three phase to ground fault occurs in the outgoing feeder. What should be the value of feeder reactor to be added to reduce the fault level by 40%? [Figure: G1 20 MVA, 11 kV, X1 = 0.1 pu; G2 30 MVA, 11 kV, X2 = 0.2 pu; G3 40 MVA, 11 kV, X3 = 0.3 pu; all three connected to a common busbar (points A, B, C); an outgoing feeder from the busbar through a circuit breaker, with the fault point on the feeder beyond the C.B.]
Answer
Convert all reactances to one base, combine the three parallel generators, and use Fault MVA . The feeder reactance is not given, so it is taken as zero (fault just beyond the C.B.).
Base: 100 MVA, 11 kV. ; .
G1 20MVA G2 30MVA G3 40MVA
0.1pu 0.2pu 0.3pu
|A |B |C
==+==========+==========+=== 11 kV
|
C.B.
|---- F
Reactances on 100 MVA base
| Generator | Calculation | (pu) |
|---|---|---|
| G1 | 0.5 | |
| G2 | 0.6667 | |
| G3 | 0.75 |
Fault level and fault current
Feeder reactor for 40 % reduction
New fault MVA MVA.
Answer: Fault level = 483.33 MVA, fault current ≈ 25.37 kA; feeder reactor ≈ 0.167 Ω (0.1379 pu on 100 MVA) brings the level down to 290 MVA.
- 2080 Bhadra · 8 marks
For the power system network given below, calculate the fault level in MVA at the outgoing feeder for a 3 phase to ground fault on the feeder. Calculate the value of reactance to be connected in the feeder in order to reduce the fault level by 50%. Ratings of the generators are: G1 = 50 MVA, 11 kV, Xg1 = 0.15 p.u.; G2 = 50 MVA, 11 kV, Xg2 = 0.3 p.u. [Figure: G1 and G2 connected to a common busbar with a single outgoing feeder]
Answer
Generators in parallel feed the fault through the bus. Fault MVA . Feeder reactance (not given) is taken as zero before adding the reactor.
Base: 50 MVA, 11 kV; . Both generators are already on 50 MVA.
G1 50MVA,0.15 G2 50MVA,0.3
| |
=====+=======+=======+==== 11 kV
| feeder (+X)
F
Fault level
Reactance for 50 % reduction
New fault MVA = 250 MVA, so
(Halving the fault level needs the total reactance to double, so the added reactance equals the existing .)
Answer: Fault level = 500 MVA; feeder reactance = 0.1 pu = 0.242 Ω (fault level becomes 250 MVA).
- 2080 Baisakh · 6 marks
Following figure shows two generators operating parallel. i) If a 3-phase to ground fault occurs on the outgoing feeder, calculate the fault current and fault level on the feeder. ii) If a 3rd generator (G3: 10MVA, 11kV, X3=0.2 pu) is added at point 'C', calculate the value of reactor to be added on the outgoing feeder so that the fault level remains same as before. [Figure: G1 20 MVA, 11 kV, X1 = 0.1 pu (path-1) and G2 20 MVA, 11 kV, X2 = 0.1 pu (path-2) connected to a common busbar at points A and B; busbar extends to point C; outgoing feeder from the busbar through a C.B., fault point 'F' on the outgoing feeder]
Answer
Fault MVA . The feeder has no reactance at first (none given).
Base: 20 MVA, 11 kV; ; .
G1 20MVA G2 20MVA G3 10MVA (added)
0.1pu 0.1pu 0.2pu
|A |B |C
==+==========+==========+=== 11 kV
|
C.B.--[X]-- F
(i) Fault current and fault level (two generators)
(ii) Reactor after adding G3
G3 on 20 MVA base: .
To keep 400 MVA the total must stay at 0.05 pu:
Answer: (i) Fault level = 400 MVA, 20.99 kA. (ii) Feeder reactor ≈ 0.00556 pu = 0.0336 Ω keeps the fault level at 400 MVA after G3 is added.
- 2079 Bhadra · 5 marks
What is the function of reactor in Power system network? Explain the ring type bus bar reactor scheme.
Answer
Function of reactor
A current-limiting reactor is a coil with high inductive reactance and negligible resistance. It limits the short-circuit current to a value that circuit breakers can interrupt, localises the fault so the rest of the bus keeps its voltage, and reduces mechanical and thermal stress on equipment.
Ring type bus-bar reactor scheme
The bus-bar is split into sections, one generator per section, and adjacent sections are joined through reactors so that the sections form a closed ring. Feeders are taken from each section.
G1 G2 G3
| | |
==[S1]===[X]===[S2]===[X]===[S3]==
| | | | | |
| feeders feeders feeders
| |
+-------------[X]--------------+
(reactor closing the ring)
Working:
- In normal operation each generator mainly feeds the load on its own section. Only small balancing currents flow through the reactors, so their voltage drop and power loss are small.
- When a fault occurs on a feeder of, say, section S2, generator G2 feeds it directly, but G1 and G3 feed it only through the reactors. The fault current from the other sections is therefore limited.
- Since each section is fed from two sides, the current through each reactor is lower than in a simple tie-bar scheme with the same reactor value.
Advantages:
- Good fault-current limitation with low losses in normal running.
- A fault is confined to one section; the voltage on other sections stays fairly high.
- Each section is supplied from both directions, so supply is more reliable than in a plain series (in-line) scheme.
Disadvantages:
- More reactors and more complex layout than the simple series bus-bar scheme.
- Load sharing between sections depends on the loads being balanced.
- 2079 Bhadra · 5 marks
For the system shown in figure below, calculate the fault level in MVA at out going feeder for a three phase to ground fault on this feeder. Calculate the value of reactance to be connected in the feeder in order to reduce the fault level by 50%. [Figure: G1 25 MVA, 11 kV, E = 1 pu, X1 = 0.15 pu and G2 25 MVA, 11 kV, E = 1 pu, X2 = 0.3 pu connected to a common busbar; outgoing feeder through a C.B. with fault point 'F' on the feeder]
Answer
Fault MVA , with pu. Feeder reactance (not given) is taken as zero before adding the reactor.
Base: 25 MVA, 11 kV; .
G1 25MVA,0.15 G2 25MVA,0.3
| |
=====+=======+=======+==== 11 kV
|
C.B.--[X]-- F
Fault level
Reactance for 50 % reduction
New fault MVA = 125 MVA.
Answer: Fault level = 250 MVA; feeder reactance = 0.1 pu = 0.484 Ω (fault level becomes 125 MVA).
- 2079 Baisakh · 6 marks
A 100 MVA generator with 10% reactance and a 200 MVA generator with 8% reactance are connected to a common bus. The fault level on bus 1 is to be restricted to 1500 MVA. If a reactor is added in between these two generators in the bus bar, then on 100 MVA base Calculate the value of reactance added.
Answer
The bus-bar is split into two sections joined by a reactor : G1 on bus 1 and G2 on bus 2. For a fault on bus 1, G1 feeds directly and G2 feeds through . Fault MVA .
Base: 100 MVA.
G1 100MVA,10% G2 200MVA,8%
| |
===[Bus 1]=====[ X ]=====[Bus 2]===
|
F (fault on bus 1)
Without reactor: pu, fault MVA MVA (too high).
With reactor: required
The two paths are in parallel:
Answer: Bus-bar reactor = 0.16 pu (16 %) on 100 MVA base. (If the bus voltage kV is known, ; e.g. at 11 kV, 0.194 Ω.)
- 2078 Bhadra · 5 marks
Two generators of capacities 40MVA, 11kV and 30MVA, 11kV having their sub transient reactance of 5% and 4% respectively operating in parallel and supplying to a common load by single feeder of reactance 2Ω. Calculate the value of reactor to be connected in series with feeder so as to reduce the fault level at the end of the feeder by 50%.
Answer
Work in per unit on a common base. Fault MVA ; ohms to pu: .
Base: 40 MVA, 11 kV; .
G1 40MVA,5% G2 30MVA,4%
| |
====+=====+=======+==== 11 kV
|
2 ohm feeder + X
|
F
Present fault level
Reactor for 50 % reduction
New fault MVA MVA, so the total reactance must double:
Answer: Present fault level = 58.23 MVA; series reactor = 0.687 pu ≈ 2.078 Ω (fault level becomes 29.11 MVA).
- 2076 Chaitra · 5 marks
A small generating station has two alternators of 2500KVA and 500KVA with percentage reactance of 8 & 6 percentage respectively. The circuit breakers are rated at 150,000kVA. Due to increase in system load it is intended to add a third generator of 10,000kVA rating and 7.5% reactance. If the system voltage is 3300volts, find the reactance X necessary to protect the C.B. [Figure: alternators A and B connected directly to the busbar, which feeds an outgoing circuit through the CB rated 150,000 kVA; the third generator C (10,000 kVA, 7.5%) is connected to the busbar through the reactor X]
Answer
The C.B. must not see a fault level above its rating (150,000 kVA). G3 is connected to the bus through reactor . For a fault on the outgoing circuit just beyond the C.B., all three machines feed the fault.
Base: 10,000 kVA, 3.3 kV; . Percentage reactance on new base: .
A 2500kVA B 500kVA C 10000kVA,7.5%
8% 6% |
| | [X]
====+===========+===========+==== 3.3 kV
|
CB 150,000 kVA
|--- F
Reactances on 10,000 kVA base
| Machine | Calculation | %X |
|---|---|---|
| A | 32 % | |
| B | 120 % | |
| C | given | 7.5 % |
: , giving fault kVA kVA (safe).
If C were connected directly: , fault kVA kVA > 150,000 kVA. So a reactor is needed.
Required reactor
Allowed total reactance:
In ohms:
Answer: Reactor ≈ 1.557 % on 10,000 kVA base ≈ 0.017 Ω in series with the new generator keeps the fault level at 150,000 kVA.
- 2076 Asoj · 8 marks
Below figure show the single line diagram of parallel operated generators. Their ratings are: G1: capacity = 50 MW, 11kV, X1 = 0.16 pu based on its rating; G2: capacity = 40 MW, 11kV, X2 = 0.12 pu based on its rating; XL = 2 ohms. [Figure: G1 (through X1) and G2 (through X2), both star-grounded, connected to a common busbar; the outgoing feeder leaves the busbar through XL] a) If a three-phase to ground fault occurs at outgoing feeder, calculate the fault current and fault power at the outgoing feeder and fault current supplied by each generator. b) Calculate the value of inductor (in mH) of the reactor to be connected in series with X2 so that both generators delivers equal amp of fault current during 3 phase to ground fault on the feeder.
Answer
Generator ratings are given in MW; they are taken as MVA (unity power factor assumed). Fault MVA ; ohms to pu: .
Base: 50 MVA, 11 kV. ; .
G1 50MW,0.16 G2 40MW,0.12
| |
X1 X2 (+ Xr in part b)
| |
====+=======+=======+==== 11 kV bus
|
XL = 2 ohm
|
F (3-ph to ground)
a) Fault current, fault power and generator currents
Current divides inversely as the branch reactances:
b) Reactor in series with for equal currents
Both generators feed the same bus, so they deliver equal current only when their branch reactances are equal:
Check: new pu, A, each generator supplies 1447.6 A.
Answer: (a) ≈ 2903 A, fault power ≈ 55.32 MVA, ≈ 1405 A, ≈ 1499 A. (b) ≈ 0.077 mH (0.0242 Ω).
- 2074 Chaitra · 6 marks
Two generators of capacities 40MVA, 11kV and 30 MVA, 11kV having their sub transient reactance of 5% and 4% respectively operating in parallel and supplying to a common load by single feeder of reactance 2 ohm. Calculate the value of reactor to be connected in series with feeder so as to reduce the fault level at the end of the feeder by 40%.
Answer
Work in per unit on a common base. Fault MVA ; ohms to pu: .
Base: 40 MVA, 11 kV; .
G1 40MVA,5% G2 30MVA,4%
| |
====+=====+=======+==== 11 kV
|
2 ohm feeder + X
|
F
Present fault level
Reactor for 40 % reduction
New fault MVA MVA.
Answer: Present fault level = 58.23 MVA; series reactor ≈ 0.458 pu = 1.385 Ω (fault level becomes 34.94 MVA).
- 2074 Asoj · 4+4 marks
Below figure shows 4 Nos of identical generators operating in parallel. Each generator is rated as 1600 kVA, 11kV, Xg = 0.2 pu. [Figure: G1, G2, G3, G4, each through Xg, connected to an 11 kV busbar at points A, B, C, D; an outgoing feeder from the busbar between B and C through a circuit breaker and a reactor X = 10 Ω, with a 3-phase to ground fault at its end] (i) Calculate fault current in outgoing feeder and fault current supplied by each generator. (ii) If reactors of 5 ohm each are connected between point A and B, point C and D respectively. Calculate fault current in outgoing feeder and fault current supplied by each generator.
Answer
Work in ohms at 11 kV. Phase voltage V. Fault current .
G1 G2 G3 G4
|Xg |Xg |Xg |Xg
A--[5]--B----+---C--[5]--D 11 kV bus
| ([5] only in part ii)
CB
|
X=10 ohm
|
F
(i) Without bus reactors
All four generators are directly in parallel:
Each generator supplies A. (Fault MVA MVA.)
(ii) With 5 Ω reactors between A–B and C–D
G1 and G4 now reach the feeder through 5 Ω; G2 and G3 connect directly.
The bus voltage behind the reactors is V, so
Check: A.
Answer: (i) = 460.83 A, each generator 115.21 A. (ii) = 443.57 A; G1 and G4 supply 95.16 A each, G2 and G3 supply 126.62 A each.
- 2073 Shrawan · 5 marks
The figure below shows four identical generators, each rated 11 kV, 25 MVA and each having sub-transient reactance of 16% on its own rating. Find 3-ϕ fault level at one of the outgoing feeder. Also calculate the value of reactance to be connected in the bus bar between "B" and "C" so that fault level reduces by 40%. [Figure: four generators connected to a busbar at points A, B, C, D; outgoing feeders leave the busbar, with a 3-ϕ fault on the feeder between C and D]
Answer
All four generators are identical, so work on their own base. Fault MVA .
Base: 25 MVA, 11 kV; pu; .
G1 G2 G3 G4
| | | |
A-------B---[X]----C-------D bus
|
F (feeder between C and D)
Fault level without reactor
( kA.)
Reactor between B and C for 40 % reduction
New fault MVA MVA, so pu.
With the reactor, G3 and G4 feed the fault directly ( pu) and G1, G2 feed it through ():
Answer: Fault level = 625 MVA; bus-bar reactor between B and C = 0.32 pu (32 %) on 25 MVA ≈ 1.549 Ω, giving 375 MVA.
- 2073 Shrawan · 5 marks
Why is reactor used in power system? Explain different types of reactor.
Answer
Reactors are coils with large inductive reactance and very small resistance. They are used in power systems mainly to limit short-circuit current so that circuit breakers and equipment are not over-stressed, and to localise faults.
Why reactors are used
- Fault current ; adding reactance cuts and the fault MVA, so cheaper breakers can be used.
- Keep the voltage on healthy sections from collapsing during a fault.
- Reduce mechanical forces and heating in windings during short circuits.
- Shunt reactors absorb surplus VAr on long, lightly loaded lines.
Types by construction
| Type | Feature |
|---|---|
| Air-core (dry) | Cement/concrete former, no iron; constant reactance, no saturation; used up to about 33 kV |
| Oil-immersed, air-core | Coil in oil tank; better insulation and cooling; for high voltage |
| Oil-immersed, iron-core (gapped) | Smaller size; reactance may fall at high current due to saturation |
Types by location (reactor schemes)
- Generator reactor: in series with each generator. Protects the generator, but is in circuit all the time, so causes constant voltage drop and loss. Modern generators have enough internal reactance, so it is seldom used.
- Feeder reactor: in series with each outgoing feeder. A fault on one feeder does not disturb the bus voltage much. But it gives no protection for bus faults, and causes drop and loss on each feeder.
- Bus-bar reactor: connects sections of the bus.
- Ring system: sections joined in a ring through reactors.
- Tie-bar system: each section connects through a reactor to a common tie-bar; fault current from other sections passes through two reactors.
Shunt reactor
Connected between line and earth at the end of long EHV lines to absorb charging current and limit the rise of receiving-end voltage (Ferranti effect).
- 2073 Chaitra · 6 marks
Below figure shows two Alternators operating in parallel. [Figure: G1 500 kVA, X1 = 15%, connected through a breaker to point A; G2 500 kVA, X2 = 15%, connected through a breaker to point C; points A, B, C lie on the 11 kV busbar; the feeder leaves from point B through a breaker and a reactor X = 20 ohms, with a 3 phase to ground fault on the feeder] (i) Calculate the fault current in outgoing feeder and fault current supplied by each alternator. (ii) If a reactor of 10 ohm is connected between point A and point B, calculate new fault current in outgoing feeder and fault current supplied by each alternator.
Answer
Work in ohms. Phase voltage V, and .
G1 500kVA G2 500kVA
15% 15%
| |
CB CB
| |
===A==[10]===B======C=== 11 kV
| ([10] only in part ii)
CB
|
X=20 ohm
|
F
(i) Without reactor between A and B
Each alternator supplies A.
(ii) With 10 Ω between A and B
Sharing (inversely as path reactance):
Answer: (i) = 166.47 A, each alternator 83.24 A. (ii) = 157.40 A; G1 supplies 69.17 A, G2 supplies 88.23 A.
- 2072 Kartik · 8 marks
Explain reactors used in generating stations and substations with diagram. Also discuss their merits and demerits along with field of application.
Answer
A reactor is an inductive coil with high reactance and negligible resistance. In generating stations and substations it is used to limit short-circuit current, localise faults and keep bus voltage up on healthy sections. Air-core (dry, concrete-supported) reactors are common because their reactance does not fall by saturation at high fault current.
1. Generator reactors
G1 G2 G3
| | |
[X] [X] [X]
| | |
=+=======+=======+=== bus
| |
feeders
- Merits: protects each generator from heavy fault current; useful for old machines with low reactance.
- Demerits: always carries full load current, so constant voltage drop and loss; a bus or feeder fault still affects all generators; gives no protection between feeders.
- Application: rarely used now, since modern generators have enough leakage reactance.
2. Feeder reactors
G1 G2
| |
=+===+===+===+=== bus
| |
[X] [X]
| |
feeder1 feeder2
- Merits: a fault on one feeder hardly affects bus voltage, so other feeders keep supplying; breaker ratings of feeders reduced.
- Demerits: no protection for bus-bar faults; constant drop and loss on every feeder; poor regulation.
- Application: distribution substations with many radial feeders.
3. Bus-bar reactors
(a) Ring system
G1 G2 G3
| | |
=S1===[X]===S2===[X]===S3=
| |
+----------[X]-----------+
(b) Tie-bar system
G1 G2 G3
| | |
=S1= =S2= =S3= sections
| | |
[X] [X] [X]
| | |
=+=======+=======+= tie-bar
- Merits: in normal operation little current flows through bus reactors, so loss and drop are small; a fault is confined to one section; tie-bar system lets sections be added easily, and fault current from other sections passes through two reactors in series.
- Demerits: a fault on a section gets full fault current from its own generator; tie-bar needs an extra bus; large voltage difference between sections if loads are unbalanced.
- Application: large generating stations with several sections and many generators.
Summary
| Scheme | Normal loss | Protects against |
|---|---|---|
| Generator reactor | High | Generator faults |
| Feeder reactor | High | Feeder faults |
| Bus-bar (ring/tie-bar) | Low | Faults within a section |
- 2071 Shrawan · 8 marks
Figure below shows a bus-bar reactor scheme. If a 3 phase to ground fault occurs on the outgoing feeder, calculate the fault current (in kA) supplied by each generator and fault MVA required for the circuit breaker (CB) on the feeder. Rating of generators are given as follow: G1: 30MVA, 11kV, Xg1" = 0.1 pu; G2: 50MVA, 11kV, Xg2" = 0.1 pu. [Figure: G1 (0.1 pu) and G2 (0.1 pu) on two bus-bar sections joined by a bus-bar reactor X = 0.2 ohm; the feeder leaves the G1 section through the CB]
Answer
G1 and G2 are on two bus sections joined by a bus-bar reactor. The feeder is on the G1 section; its reactance is not given, so the fault is taken just beyond the CB. G1 feeds directly; G2 feeds through the bus reactor. Fault MVA .
Base: 50 MVA, 11 kV; ; .
G1 30MVA,0.1 G2 50MVA,0.1
| |
===[Sec 1]====[X=0.2 ohm]====[Sec 2]===
|
CB
|--- F
Reactances on 50 MVA base
Fault current and fault MVA
Current from each generator
Answer: G1 supplies ≈ 15.75 kA, G2 ≈ 14.37 kA (total 30.11 kA); the feeder CB must be rated for about 574 MVA.
- 2071 Chaitra · 5 marks
In figure below a bus-bar reactor scheme with four generators. If a 3 phase to ground fault occurs on the outgoing feeder, calculate the fault current (in kA) supplied by each generator and fault MVA required for the circuit breaker (CB) on the feeder. Rating of generators are given as follow: G1/G2: [?]MVA, 11kV, Xg1" = 0.2 pu; G3/G4: [?]MVA, 11kV, Xg2" = 0.1 pu. [Figure: G1 (0.2 pu) and G2 (0.2 pu) on one bus-bar section, G3 (0.1 pu) and G4 (0.1 pu) on the other, the two sections joined by a bus-bar reactor X = 0.2 ohms; the feeders leave the G1/G2 section through the CB] (Generator MVA ratings are unreadable in the scan.)
Answer
The generator MVA ratings are not readable, so assume G1 = G2 = 30 MVA and G3 = G4 = 50 MVA, all 11 kV (the method is the same for any rating). The feeder reactance is not given, so the fault is taken just beyond the CB. G1 and G2 feed directly; G3 and G4 feed through the bus-bar reactor.
Base: 50 MVA, 11 kV; ; .
G1 G2 G3 G4
0.2 0.2 0.1 0.1
| | | |
==[Section 1]==[X=0.2 ohm]==[Section 2]==
|
CB
|--- F
Reactances on 50 MVA base
Fault MVA and fault current
Current from each generator
Answer (with the assumed ratings): G1, G2 ≈ 7.87 kA each; G3, G4 ≈ 9.89 kA each; total 35.53 kA; CB fault rating ≈ 677 MVA.
- 2070 Chaitra · 8 marks
Explain different reactor schemes used in generating station and substations.
Answer
Current-limiting reactors are placed at chosen points of a station so that the short-circuit current is limited and a fault in one part does not collapse the voltage of the whole station. The main schemes are below.
1. Generator reactor scheme
Reactor in series with each generator, between the generator and the bus.
G1 G2 G3
[X] [X] [X]
| | |
=+===+===+===+===+= bus
| |
feeders
- Protects the generator against faults beyond it.
- Disadvantage: full load current always flows, so constant voltage drop and loss; a feeder fault still lowers the whole bus voltage. Now seldom used, as modern machines have high reactance.
2. Feeder reactor scheme
Reactor in series with each outgoing feeder.
G1 G2
| |
=+===+===+===+= bus
[X] [X]
| |
feeder feeder
- A feeder fault is limited by its own reactor; the bus voltage stays nearly normal, so other feeders are not disturbed.
- Disadvantage: no protection against bus faults; constant drop and loss in each feeder.
3. Bus-bar reactor schemes
The bus is divided into sections, each with a generator; sections are joined through reactors. In normal operation little current passes between sections, so losses are small.
(a) Ring system: each section connected to the next through a reactor, forming a ring.
G1 G2 G3
=S1===[X]===S2===[X]===S3=
| |
+----------[X]-----------+
A fault on one section is fed by the other generators only through reactors. Each section is fed from both sides, so it is more reliable than a straight in-line arrangement.
(b) Tie-bar system: each section is connected through its own reactor to a common tie-bar.
=S1= =S2= =S3= sections
[X] [X] [X]
| | |
=+=======+=======+= tie-bar
Fault current from any other section passes through two reactors in series, so each reactor can be about half the value needed in a ring system. New sections are added easily. It needs an additional bus-bar.
Comparison
| Scheme | Normal loss/drop | Main merit | Main demerit |
|---|---|---|---|
| Generator | High | Protects generator | Constant loss |
| Feeder | High | Bus voltage held on feeder fault | No bus-fault protection |
| Ring bus | Low | Fault confined to section | Unbalanced loads cause section voltage difference |
| Tie-bar | Low | Two reactors in fault path; easy extension | Extra tie-bar cost |
- 2069 Chaitra · 8 marks
Figure below shows the single line diagram of parallel operated generators. Their ratings are: G1: capacity = 50 MW, 11kV, X1 = 0.16 pu based on its rating; G2: capacity = 50MW, 11kV, X2 = 0.16 pu based on its rating; Xl = 2 ohms. [Figure: G1 (through X1) and G2 (through X2), both star-grounded, connected to a common busbar; the feeder leaves the busbar through Xl] Calculate the fault current in the feeder during 3 phases to ground fault on the feeder. Calculate the value of inductance (in mH) of the reactor to be connected in series with Xl so that the fault current decreases by 40%.
Answer
Ratings in MW are taken as MVA (unity power factor). Fault current ; ohms to pu: .
Base: 50 MVA, 11 kV; ; .
G1 50MW,0.16 G2 50MW,0.16
| |
====+======+=======+==== 11 kV
|
Xl=2 ohm + new L
|
F
Fault current
(Fault MVA MVA.)
Reactor for 40 % reduction in fault current
New A, so the total reactance must become :
Answer: ≈ 2895 A; series reactor ≈ 1.462 Ω, i.e. L ≈ 4.65 mH (fault current falls to about 1737 A).
Questions from Old Question Collection (EE 703) (IOE EE 703 exam papers from 2073 Shrawan to 2082 Baisakh) and Question bank (ioesolutions) (IOE EE 703 exam papers from 2069 Chaitra to 2073 Chaitra). Answers are written for this site; check them against your class notes.
Chapter titles and hours from the IOE syllabus ↗