Skip to main content

Chapter 5 · 6 hours

Micro and small hydro power systems

Practice questions

Practice questions and answers

5 exam-style questions on this chapter, written for this site from the official syllabus. We haven’t found past IOE papers for this subject yet; if you have some, share them in the community.

  • Practice · 6 marks

Explain the main components of a run-of-river micro hydropower scheme with a layout sketch. How are hydropower plants classified by capacity and by head?

Answer

A run-of-river scheme diverts part of the stream flow through a channel and penstock to a turbine and returns it to the river, with little or no storage.

Layout

  river  weir/intake
   ~~~~>[==]--> canal --> [forebay/
                           settling tank]
                              \  penstock
                               \  (gross
                                \  head)
                         [powerhouse]
                         turbine+gen --> load
                           tailrace--> river

Components

  • Diversion weir and intake: raises the water level, directs flow into the canal; trash rack and gate keep out debris and control flow.
  • Headrace canal (or pipe): carries water with a small slope to the forebay.
  • Settling basin (desilting tank): removes sand and silt to protect the turbine.
  • Forebay: small tank at the head of the penstock; gives storage for load changes and has a trash rack, spillway and air vent.
  • Penstock: steel, HDPE or PVC pipe taking water down to the turbine; designed for pressure and water hammer.
  • Powerhouse: turbine (Pelton, cross-flow, Turgo, propeller, or pump as turbine), governor or electronic load controller, generator, and control panel.
  • Tailrace: returns the water to the river.
  • Transmission and distribution lines to users.

Classification

BasisClassRange (commonly used)
CapacityPicobelow 5 kW
Micro5–100 kW
Mini100 kW–1 MW
Small1–10 MW
HeadLowbelow 15 m
Medium15–50 m
Highabove 50 m

Class limits vary by country and textbook. Low-head sites use Kaplan or cross-flow turbines; high-head sites use Pelton or Turgo turbines.

  • Practice · 5 marks

Describe the investigations required to select a site for a micro hydropower plant. Explain any three methods of measuring the head of a site.

Answer

Site investigation decides whether the potential flow and head can be developed safely and cheaply.

Investigations

  1. Reconnaissance: study of maps and a field walk to find possible intake, canal, forebay and powerhouse positions and the demand (load) of the nearby village.
  2. Head measurement: gross head between intake water level and tailrace level.
  3. Flow measurement: dry-season (minimum) and mean flow, from direct measurement or hydrological estimates.
  4. Geology and soil: stable slopes, no landslide or leaking ground along canal and penstock; foundation for powerhouse and anchor blocks.
  5. Layout and cost: length of canal and penstock, access, flood level of the powerhouse, distance to load.
  6. Environment and water rights: impact on downstream users and fish, irrigation and drinking needs.

Head measurement methods

  • Water-filled tube (pipe) and pressure gauge: a long flexible tube filled with water is laid down the slope; the gauge reading at the lower end gives the head, H=p/(ρg)H = p/(\rho g). Reading is taken in steps for long drops.
  • Spirit level and measuring stick (or Abney level): a level is used to measure the height difference in successive steps along the slope and the steps are added. It is cheap and quite accurate for short drops.
  • Altimeter or GPS: readings at the top and bottom give an approximate height difference, with an error of a few metres, so it is used in the first survey only.
  • Dumpy level / theodolite: gives the most accurate result in the detailed survey.

The net head is the gross head minus friction and bend losses in the penstock (typically 5–10 % of gross head).

  • Practice · 6 marks

Explain the methods used to measure the flow of a small stream for a micro hydro plant (bucket, float, weir, salt dilution and current meter). What is a flow duration curve and how is it used in selecting the design flow?

Answer

Bucket method

The whole stream is diverted into a container of known volume and the filling time is measured. Q=V/tQ = V/t. It is accurate and used for very small flows (below about 10 L/s).

Float (velocity-area) method

Mark a straight length of channel (say 10–20 m), measure the time tt for a float to travel it, and the average cross-sectional area AA. Surface velocity vs=L/tv_s = L/t; mean velocity v=k vsv = k\,v_s with k≈0.8k \approx 0.8–0.85. Q=A vQ = A\,v. It is simple but approximate.

Weir method

A sharp-edged rectangular or V-notch weir is built across the stream and the head HH over the crest is measured. For a rectangular weir with end contractions Q=1.84 (L−0.1nH)H3/2Q = 1.84\,(L - 0.1nH)H^{3/2} and for a 90° V-notch Q=1.4H5/2Q = 1.4H^{5/2} (m³/s, metres). Accurate for small and medium streams.

Salt dilution method

A known mass of salt is dissolved and poured into the stream at one point, and the conductivity is recorded downstream where it is fully mixed. The area under the conductivity-time curve gives QQ. It suits turbulent mountain streams where other methods are difficult.

Current meter

A propeller meter measures velocity at several points (usually at 0.6 of depth) in verticals across the section. Q=∑viAiQ = \sum v_i A_i (velocity-area method). It gives the best accuracy but needs equipment.

Flow duration curve (FDC)

It is a plot of flow against the percentage of time (or days) the flow is equalled or exceeded, constructed from daily or monthly flow records sorted in descending order.

 Q
 |\
 | \___
 |     \____
 |          \______
 +------------------ % time
 0       50      100

For micro hydro the design flow is normally taken at the flow available 90–95 % of the time (dry season) so that power is dependable, and the area under the curve gives the energy available.

  • Practice · 6 marks

A micro hydro site has a gross head of 60 m and a design flow of 0.15 m³/s. Penstock and other losses are 8 % of gross head. The turbine efficiency is 80 % and the generator efficiency is 92 %. Calculate (a) the net head, (b) the hydraulic power, (c) the electrical output, and (d) the annual energy if the plant factor is 0.6.

Answer

(a) Net head

Hn=Hg−hL=60−0.08(60)=55.2 mH_n = H_g - h_L = 60 - 0.08(60) = 55.2\ \text{m}

(b) Hydraulic power at turbine inlet

Ph=ρgQHn=1000×9.81×0.15×55.2=81 227 W=81.2 kWP_h = \rho g Q H_n = 1000 \times 9.81 \times 0.15 \times 55.2 = 81\,227\ \text{W} = 81.2\ \text{kW}

(c) Electrical output

ηo=0.80×0.92=0.736\eta_o = 0.80 \times 0.92 = 0.736 Pe=ηoPh=0.736×81.2=59.8 kWP_e = \eta_o P_h = 0.736 \times 81.2 = 59.8\ \text{kW}

The scheme falls in the micro hydro range (5–100 kW). Gross hydraulic power was ρgQHg=88.3\rho g Q H_g = 88.3 kW, so overall efficiency from the gross head is 59.8/88.3=67.7 %59.8/88.3 = 67.7\ \%.

(d) Annual energy

E=Pe×8760×PF=59.8×8760×0.6=3.14×105 kWhE = P_e \times 8760 \times PF = 59.8 \times 8760 \times 0.6 = 3.14\times10^{5}\ \text{kWh}

Answer: Hn=55.2H_n = 55.2 m; Ph=81.2P_h = 81.2 kW; Pe=59.8P_e = 59.8 kW; E≈3.14×105E \approx 3.14 \times 10^5 kWh (314 MWh) per year.

  • Practice · 6 marks

(a) A rectangular sharp-crested weir of crest length 0.6 m with two end contractions has a measured head of 0.18 m. Find the flow using Francis' formula Q=1.84 (L−0.1nH)H3/2Q = 1.84\,(L - 0.1nH)H^{3/2} (SI units). (b) In a rectangular channel of width 1.2 m and mean water depth 0.40 m, a float takes 25 s to travel 20 m. Taking the mean velocity as 0.85 times the surface velocity, find the flow.

Answer

(a) Weir

Here L=0.6L = 0.6 m, n=2n = 2, H=0.18H = 0.18 m.

Effective length: L−0.1nH=0.6−0.1(2)(0.18)=0.564L - 0.1nH = 0.6 - 0.1(2)(0.18) = 0.564 m

H3/2=0.181.5=0.0764H^{3/2} = 0.18^{1.5} = 0.0764

Q=1.84×0.564×0.0764=0.0793 m3/sQ = 1.84 \times 0.564 \times 0.0764 = 0.0793\ \text{m}^3/\text{s}

That is 79 litres per second.

(b) Float

Surface velocity:

vs=2025=0.80 m/sv_s = \frac{20}{25} = 0.80\ \text{m/s}

Mean velocity:

v=0.85×0.80=0.68 m/sv = 0.85 \times 0.80 = 0.68\ \text{m/s}

Area: A=1.2×0.40=0.48A = 1.2 \times 0.40 = 0.48 m².

Q=Av=0.48×0.68=0.326 m3/sQ = A v = 0.48 \times 0.68 = 0.326\ \text{m}^3/\text{s}

Answer: (a) Q=0.0793Q = 0.0793 m³/s (79 L/s); (b) Q=0.326Q = 0.326 m³/s (326 L/s).

Written from the official syllabus. Questions and answers are written for this site; check them against your class notes.

Chapter titles and hours from the IOE syllabus ↗