Chapter 5 · 6 hours
Micro and small hydro power systems
Practice questions
Practice questions and answers
5 exam-style questions on this chapter, written for this site from the official syllabus. We haven’t found past IOE papers for this subject yet; if you have some, share them in the community.
- Practice · 6 marks
Explain the main components of a run-of-river micro hydropower scheme with a layout sketch. How are hydropower plants classified by capacity and by head?
Answer
A run-of-river scheme diverts part of the stream flow through a channel and penstock to a turbine and returns it to the river, with little or no storage.
Layout
river weir/intake
~~~~>[==]--> canal --> [forebay/
settling tank]
\ penstock
\ (gross
\ head)
[powerhouse]
turbine+gen --> load
tailrace--> river
Components
- Diversion weir and intake: raises the water level, directs flow into the canal; trash rack and gate keep out debris and control flow.
- Headrace canal (or pipe): carries water with a small slope to the forebay.
- Settling basin (desilting tank): removes sand and silt to protect the turbine.
- Forebay: small tank at the head of the penstock; gives storage for load changes and has a trash rack, spillway and air vent.
- Penstock: steel, HDPE or PVC pipe taking water down to the turbine; designed for pressure and water hammer.
- Powerhouse: turbine (Pelton, cross-flow, Turgo, propeller, or pump as turbine), governor or electronic load controller, generator, and control panel.
- Tailrace: returns the water to the river.
- Transmission and distribution lines to users.
Classification
| Basis | Class | Range (commonly used) |
|---|---|---|
| Capacity | Pico | below 5 kW |
| Micro | 5–100 kW | |
| Mini | 100 kW–1 MW | |
| Small | 1–10 MW | |
| Head | Low | below 15 m |
| Medium | 15–50 m | |
| High | above 50 m |
Class limits vary by country and textbook. Low-head sites use Kaplan or cross-flow turbines; high-head sites use Pelton or Turgo turbines.
- Practice · 5 marks
Describe the investigations required to select a site for a micro hydropower plant. Explain any three methods of measuring the head of a site.
Answer
Site investigation decides whether the potential flow and head can be developed safely and cheaply.
Investigations
- Reconnaissance: study of maps and a field walk to find possible intake, canal, forebay and powerhouse positions and the demand (load) of the nearby village.
- Head measurement: gross head between intake water level and tailrace level.
- Flow measurement: dry-season (minimum) and mean flow, from direct measurement or hydrological estimates.
- Geology and soil: stable slopes, no landslide or leaking ground along canal and penstock; foundation for powerhouse and anchor blocks.
- Layout and cost: length of canal and penstock, access, flood level of the powerhouse, distance to load.
- Environment and water rights: impact on downstream users and fish, irrigation and drinking needs.
Head measurement methods
- Water-filled tube (pipe) and pressure gauge: a long flexible tube filled with water is laid down the slope; the gauge reading at the lower end gives the head, . Reading is taken in steps for long drops.
- Spirit level and measuring stick (or Abney level): a level is used to measure the height difference in successive steps along the slope and the steps are added. It is cheap and quite accurate for short drops.
- Altimeter or GPS: readings at the top and bottom give an approximate height difference, with an error of a few metres, so it is used in the first survey only.
- Dumpy level / theodolite: gives the most accurate result in the detailed survey.
The net head is the gross head minus friction and bend losses in the penstock (typically 5–10 % of gross head).
- Practice · 6 marks
Explain the methods used to measure the flow of a small stream for a micro hydro plant (bucket, float, weir, salt dilution and current meter). What is a flow duration curve and how is it used in selecting the design flow?
Answer
Bucket method
The whole stream is diverted into a container of known volume and the filling time is measured. . It is accurate and used for very small flows (below about 10 L/s).
Float (velocity-area) method
Mark a straight length of channel (say 10–20 m), measure the time for a float to travel it, and the average cross-sectional area . Surface velocity ; mean velocity with –0.85. . It is simple but approximate.
Weir method
A sharp-edged rectangular or V-notch weir is built across the stream and the head over the crest is measured. For a rectangular weir with end contractions and for a 90° V-notch (m³/s, metres). Accurate for small and medium streams.
Salt dilution method
A known mass of salt is dissolved and poured into the stream at one point, and the conductivity is recorded downstream where it is fully mixed. The area under the conductivity-time curve gives . It suits turbulent mountain streams where other methods are difficult.
Current meter
A propeller meter measures velocity at several points (usually at 0.6 of depth) in verticals across the section. (velocity-area method). It gives the best accuracy but needs equipment.
Flow duration curve (FDC)
It is a plot of flow against the percentage of time (or days) the flow is equalled or exceeded, constructed from daily or monthly flow records sorted in descending order.
Q
|\
| \___
| \____
| \______
+------------------ % time
0 50 100
For micro hydro the design flow is normally taken at the flow available 90–95 % of the time (dry season) so that power is dependable, and the area under the curve gives the energy available.
- Practice · 6 marks
A micro hydro site has a gross head of 60 m and a design flow of 0.15 m³/s. Penstock and other losses are 8 % of gross head. The turbine efficiency is 80 % and the generator efficiency is 92 %. Calculate (a) the net head, (b) the hydraulic power, (c) the electrical output, and (d) the annual energy if the plant factor is 0.6.
Answer
(a) Net head
(b) Hydraulic power at turbine inlet
(c) Electrical output
The scheme falls in the micro hydro range (5–100 kW). Gross hydraulic power was kW, so overall efficiency from the gross head is .
(d) Annual energy
Answer: m; kW; kW; kWh (314 MWh) per year.
- Practice · 6 marks
(a) A rectangular sharp-crested weir of crest length 0.6 m with two end contractions has a measured head of 0.18 m. Find the flow using Francis' formula (SI units). (b) In a rectangular channel of width 1.2 m and mean water depth 0.40 m, a float takes 25 s to travel 20 m. Taking the mean velocity as 0.85 times the surface velocity, find the flow.
Answer
(a) Weir
Here m, , m.
Effective length: m
That is 79 litres per second.
(b) Float
Surface velocity:
Mean velocity:
Area: m².
Answer: (a) m³/s (79 L/s); (b) m³/s (326 L/s).
Written from the official syllabus. Questions and answers are written for this site; check them against your class notes.
Chapter titles and hours from the IOE syllabus ↗